Granville D&H Trail Crossings and Resurfacing Recommendations — DRAFT

DRAFT Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

Memo To: Mr. Jack Mance, Senior Transportation Planner Date: February 21, 2025
Adirondack/Glens Falls Transportation Council

From: Barton & Loguidice, D.P.C. (B&L) File: 1896.011.001

I. Introduction:
On behalf of the Village of Granville, the Adirondack/Glens Falls Transportation Council (A/GFTC) and
Barton & Loguidice, DPC (B&L) have prepared this Technical Memorandum to evaluate potential
improvements for a 4.75-mile section of the Delaware and Hudson (D&H) Rail Trail from Depot Street to
the Vermont border. The Village, in coordination with the Lake Champlain-Lake George Regional
Planning Board and the US EPA, recently completed a Community Action Plan for the Recreation
Economy for Rural Communities program. This plan established several goals and action items in the
Village including conducting a signage assessment and to improve the rail trail. Some improvements
have already been implemented including installing benches and landscaping along the trail. This report
provides a comprehensive overview of the existing conditions of the surface of the D&H Rail Trail and
roadway crossings within the noted limits of the Rail Trail and provides improvement recommendations.

Figure I-1: Project Location
Source: Google Earth

Page | 1

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

II. Existing Conditions
This section contains general information about the existing conditions along the D&H Rail Trail project
corridor. The existing conditions were assessed using ArcGIS Survey123, a mobile application enabling
real-time data collection. B&L personnel visited the trail corridor on August 29, 2024 to assess and
document the existing conditions utilizing the application to record data on surface conditions, signage,
pedestrian crossings, and other significant elements along the corridor. Each recorded data point was
supplemented with a photograph and a corresponding GPS location.

A. Land Use and Community Context
The D&H Rail Trail is a recreational resource, extensively used by
pedestrians, cyclists, and joggers, as well as functioning as a
snowmobile trail during the winter season. The trail exhibits
significant variability in its conditions and surrounding land use.
Starting at Depot St., the northern end of the study limits, the trail
passes through a densely wooded area. To the north of Granville,
it is surrounded by open fields and residential homes, with the
landscape characterized by natural forest and open terrain. As it
progresses southward, the trail enters the downtown setting, where
it passes through the central part of the Village, integrating with local
community features such as small businesses, restaurants, stores and residential homes. Southeast of
Village the segment of the trail transitions back to a mixed landscape of open fields and densely wooded
areas.

B. Trail Characteristics
The geometry of the trail, including surface conditions, width, and clear width, were systematically
documented throughout the corridor. Beginning at Depot Street, it was observed that the original gravel
surface has been overtaken by grass in many areas, although the trail is still mowed and maintained to
its full width in most locations. Despite the growth of
grass altering the surface composition and covering
parts of the original surface, the overall effective width
of the trail remains fully maintained. This grass-covered
surface extends for the first 1.5 miles from Depot St to
North St. (CR 24). Then from CR 24 to Main Street (0.5
miles), the trail surface was predominantly gravel,
though grass had started to impede from the edges.
From the Station House to Water Street (0.2 miles), the
trail was entirely grass with no visible remnants of the
former trail surface or rail bed. The trail then crosses
over the Mettawee River via a bridge before meeting
up with Water Street. This 0.1 mile section of the trail
has a gravel surface on each approach to the bridge.
From Morrison Ave. to Church Street, a 4 ft. wide
asphalt path was present (0.06 mi). For the following 0.5 miles southeast of Village, the trail remained
largely grass-covered, the final 1.9 miles that continued to the south consisted mainly of gravel, with
occasional grass strips along the center in certain sections.

Figure II-1 – D&H Trail Next to
Station house Bed and Breakfast.

Figure II-2- Trail Section Between Depot St. and CR 24

Page | 2

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

The clear width was measured from the edge of the
gravel trail to the edge of the adjacent vegetation,
with the total clear width calculated by summing the
clear space on both sides of the trail from the edge
of the trail to the edge of the pavement. The trail
width refers to the distance across the gravel surface
itself. In cases where the trail shoulder was
distinguishable, the clear width plus the trail width
were combined to determine the effective width. In
areas where no clear boundary existed between the
shoulder and trail surface, the total distance from
the vegetation on one side to the vegetation on the
other was recorded as the effective width (See
Figure II-3 for details). The average effective width is
approximately 19 ft., with a minimum recorded width of 10 ft. at one location between Depot St and CR
24.

The right-of-way (ROW) along the trail varies considerably, ranging from sections as narrow as 20 ft. to
others as wide as 130 ft. Across the evaluated section, the average ROW was determined to be 72 ft.

C. Signage
A comprehensive assessment of signage along the D&H Rail Trail identified a total of 113 signs. This
includes signage intended for both trail users and motorists at roadway crossings. Specifically, 33 signs
are pedestrian crossing warning signs intended to alert drivers. Six of the seven crossings had some level
of crossing signage for drivers. Additionally, 50 signs conform to the Manual on Uniform Traffic Control
Devices (MUTCD) standards, providing clear guidance and information for trail users. The remaining 30
signs serve various functions, including navigational aids and informational displays about the trail.

D. Crossings
A total of seven roadway crossings of the trail were reviewed for
conformance with the current design standards for multi-use trail
crossings, including the American Association of State Highway
and Transportation Officials (“AASHTO”) Guide for the
Development of Bicycle Facilities 2012, NYSDOT Highway Design
Manual (HDM), 2023 Manual on Uniform Traffic Control Devices
(MUTCD), FHWA Guide for Improving Pedestrian Safety at
Uncontrolled Crossing locations, and the Empire State Trail Design
Guide (further referred to as the “Trail Design Standards”). Of
those evaluated, five crossings included painted crosswalks to
enhance visibility of the crossing location. The trail crossing of CR
24 was the only crossing with advance warning signage for vehicles
and this signage was only present for southbound traffic. Additionally, several intersections featured
pedestrian crossing signs but lacked MUTCD-compliant elements, such as signage on both sides of the
crosswalk and both front and back of the sign post. Table II-1 provides a detailed summary of the
signage documented at each crossing.

Figure II-3: Measurement Diagram

Figure II-4 – Water Street Crossing

Page | 3

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

Trail Crossing Signage􀀃
Intersecting􀀃
Street􀀃Sign􀀃
Posts􀀃
Trail Crossing􀀃
W11􀀃15􀀃W16-7p(Bicycle/􀀃(Arrow)􀀃Ped)􀀃
Advance Warning􀀃
W11􀀃15Sign􀀃W11-15p (Trail􀀃(Bicycle/􀀃Posts􀀃X-ing)􀀃Ped)􀀃
W16-9p􀀃
(Ahead)􀀃
North Street􀀃
Main Street􀀃
Water Street􀀃
Morrison Ave􀀃
Church􀀃
Street􀀃
E Potter Ave􀀃
Andrews lane􀀃
2􀀃
2􀀃
1􀀃
2􀀃
2􀀃
2􀀃
0􀀃
4􀀃4􀀃
4􀀃4􀀃
1􀀃1􀀃
2􀀃2􀀃
2􀀃2􀀃
2􀀃2􀀃
0􀀃0􀀃
1􀀃1􀀃1􀀃
0􀀃0􀀃0􀀃
0􀀃0􀀃0􀀃
0􀀃0􀀃0􀀃
0􀀃0􀀃0􀀃
0􀀃0􀀃0􀀃
0􀀃0􀀃0􀀃
1􀀃
0􀀃
0􀀃
0􀀃
0􀀃
0􀀃
0􀀃

Table II-1-Trail Crossing Signage

The roadway classifications and traffic data for each roadway crossing were reviewed on the NYSDOT
Traffic Data Viewer to assist in the analysis of each roadway crossing on the D&H Rail Trail. See table III-2
below.

Trail Crossing Traffic Data􀀃
Intersecting Street􀀃Roadway􀀃Posted Speed􀀃AADTClassification􀀃Limit (MPH)􀀃
85th Percentile􀀃
Speed (MPH)􀀃
North Street􀀃
Main Street􀀃
Water Street􀀃
Morrison Ave􀀃
Church Street􀀃
E Potter Ave􀀃
Andrews􀀃lane􀀃
Rural Minor Collector􀀃2,373􀀃30􀀃
Rural Minor Collector􀀃4,346􀀃30􀀃
Rural Local􀀃No Data􀀃30*􀀃
Rural Local􀀃No Data􀀃30*􀀃
Rural Major Collector􀀃2,997􀀃30􀀃
Rural Local􀀃No Data􀀃30􀀃
Rural Local􀀃No Data􀀃30*􀀃
38.2􀀃
29.7􀀃
No Data􀀃
No Data􀀃
31.6􀀃
No Data􀀃
No Data􀀃

*No speed limit posted, 30mph assumed based on roadway characteristics

Table II-2- Crossing Traffic Data

Each crossing was also assigned an accessibility rating based on compliance with the Americans with
Disabilities Act (ADA). Elements of ADA compliance include the presence of a curb ramp, detectable
warning strips (DWS), slope of curb ramp, whether or not the pavement surface is flush with the edge of
the curb ramp, and the overall condition of the pavement in the crosswalk. The crossing located on Main
Street was the only crossing identified as fully accessible, meeting all relevant ADA criteria including curb
ramps on both sides of the crossing. The remaining crossings were rated as partially accessible,
indicating that improvements are needed to achieve full ADA compliance.

Page | 4

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

In addition to the roadway crossings, there were six driveway crossings, including one that passes
through an active farm where vehicles, livestock, and heavy equipment frequently cross. The high
volume and type of traffic at this crossing may impact trail user safety, warranting further consideration
in the trail’s design and operational planning. The remaining driveway crossings appear to exhibit low
traffic volumes and are not expected to significantly affect trail user access or safety.

Figure II-5 Crossing though active farmland

E. Other Notable Features
Additional features documented along the trail include three bridges and three culverts. A New York
State Department of Environmental Conservation (DEC) posting was also observed, located in a small
stream next to Saint-Gobain Performance Plastics indicating an ongoing spill investigation in the area.

Within the farm section located at the Kenneth
property (parcel ID 108.-1-3.4), the farm’s operations
and much of its infrastructure are situated within the
trail right-of-way, utilizing dirt roadways on and across
the existing trail. The farm appears to use the trail ROW
for its regular operations as well as an area for storing
cow hutches. Additionally, the trail features a cow pass
located beneath it, which is a component of the farm’s
infrastructure. The cow pass stands approximately 7 ft.
high, resulting in a steep and unstable slope that trail
users must navigate. Figure II-7 displays a photograph of
the steep slope. It should be noted that this location is
outside of the Village of Granville and is assumed to be
under the jurisdiction of NYS Office of Parks and
Recreation. As such, no improvements are changes have
been proposed under the auspices of the current analysis.

Figure II-6 – Steep slope

Page | 5

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

III. Recommended Improvements
A. Trail Surface
This trail surface comparison will consider factors such as durability, maintenance requirements, and
user safety to determine the most appropriate material for ensuring long-term functionality, improved
usability, and overall trail sustainability. The trail surface material selected should be installed to
establish a 10-12 ft. wide trail with 2-5 ft. shoulders on each side, as recommended by the Empire State
Trail Design Guide. Additionally, this design guide recommends that trails accommodating snowmobile
use should have a width of 12-14 ft. (10 ft. minimum) to ensure safe operations during winter. As noted
in the field reconnaissance, the existing average effective width is 19 ft., therefore it is feasible to
establish a recommended trail width of 12 ft. with 2 ft. shoulders along this corridor.

1. Asphalt Surface
An Asphalt surface provides a smooth, durable top course that enhances accessibility for a variety of
users, including pedestrians, cyclists, and individuals with mobility impairments. Asphalt is well-suited
for trails due to its longevity and minimal maintenance requirements. The smooth, paved surface also
improves user comfort and safety, especially for cyclists, in-line skaters, and wheelchair users, reducing
the likelihood of rutting and
erosion.

Asphalt is best suited for
snowmobile trails in areas where
snow accumulates 1 ft. or more
and consistently covers the
surface. This snow layer acts as a
protective barrier, reducing wear
on the asphalt from snowmobiles’
studded tracks, which could
otherwise wear on the trail
surface.

Figure III-1-Kingston Rail Trail, Ulster County

Asphalt also offers a significant
advantage over gravel in terms of snow removal efficiency in areas that are not used as a snowmobile
trail. Plowing a paved surface is more straightforward and results in less wear on maintenance
equipment, as the smooth solid surface allows plows to glide over its surface. Furthermore, asphalt is
less susceptible to damage from snowmobiles compared to gravel, which can be displaced or eroded
during winter use, leading to a more durable and lower-maintenance surface throughout the year.

Page | 6

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

2. Crushed Stone
An alternative to the traditional hard surface material, is a crushed stone aggregate surface course that
is bound by clay particles. The natural materials of this surface course appeal to the environmental
setting of the project by maintaining the natural aesthetic and feel of the D&H corridor, blending with
the surrounding environment. Examples of this durable stone course system use includes the D&H Canal
Trail in the Town of Mamakating, NYS OPRHP Minnewaska State Park, the Rockefeller State Park
Preserve, and the Ashokan Rail Trail in Ulster County.

Figure III-2 D&H Canal Trail, Town of Mamakating

Crushed Stone paths provide a durable and relatively flat surface, making them suitable for various
types of trail users. While crushed stone trails can be ADA compliant, they may not offer the same level
of convenience and smoothness as other surface materials, such as asphalt. Crushed stone is susceptible
to vegetation growth impeding the trail width from the sides of the trail, which can occur if the trail is
not regularly maintained.

Page | 7

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

3. Cost Estimate
The cost estimate below for both an asphalt and stone surfaced trail assumes that full excavation of the
existing trail material is needed due to the heavy presence of organic material that is present within the
existing trail limits. Constructing the trail on top of the existing material could lead to pre-mature failure
of the trail system. Additionally, the clearing and grubbing line item includes trimming back the
vegetation that is encroaching onto the trail corridor. The estimate includes the cost of resurfacing the
entire length of the trail system. Cost per mile have been included below the table as well to facilitate
phase improvement planning.

Village of Granville -D&H Rail Trail Resurfacing
Cost Estimate
Items of Work / Road Crossing Asphalt Trail
Surface
Crushed
Stone
Surface
Lighting
(Entire Trail)
ASPHALT SURFACE COURSE $ 1,127,471 —
CRUSHED STONE TOP COURSE -$ 386,031 $ –
SUBBASE STONE $ 501,600 $ 501,600 $ –
EXCAVATION $ 445,867 $ 445,867 $ –
CLEARING AND GRUBBING $ 50,000 $ 50,000 $ –
LIGHTING $ -$ -$ 1,400,000
MISCELLANEOUS —
ITEMIZED CONSTRUCTION SUBTOTAL: $ 2,125,000 $ 1,384,000 $ 1,400,000
FIELD CHANGE ORDER (5%)
MOBILIZATION (USE 4%)
CONTINGENCY / RISK (10%)
$ 106,250 $ 69,200 $ 70,000
$ 89,300 $ 58,200 $ 58,800
$ 212,500 $ 138,400 $ 140,000
PRIVATE CONTRACTOR SUBTOTAL: $ 2,534,000 $ 1,650,000 $ 1,669,000
ENGINEERING / APPROVALS $ 506,800 $ 330,000 $ 333,800
CONSTRUCTION INSPECTION $ 304,080 $ 198,000 $ 200,280
FEDERAL-AID PROJECT COSTS: $ 3,344,900 $ 2,178,000 $ 2,203,100

Cost / Mile
ITEMIZED CONSTRUCTION SUBTOTAL: $ 448,000 $ 292,000 $ 295,000
PRIVATE CONTRACTOR SUBTOTAL: $ 534,000 $ 348,000 $ 352,000
FEDERAL-AID PROJECT COSTS: $ 705,000 $ 459,000 $ 464,000
Table III-1: Trail Resurfacing Cost Estimate

Page | 8

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

B. Trail Crossings
The seven (7) road crossings were evaluated by assessing the existing features that are present at each
location, such as signage, pavement markings, detectable warning strips, etc. The crossings were then
compared to standardized crossing features established by the Trail Design Standards to determine if
features are missing and what improvements should be made to each crossing.

An ideal at-grade roadway crossing has a variety of features present that warn the trail users that there
is a roadway crossing present, and that warns roadway users that pedestrians and bicyclists may be
crossing the roadway. The emphasis of safety should be placed on both interactions equally as it is both
users responsibility to operate safely at crossings. Nearly all of the crossings evaluated need some level
of improvements to the warning signs posted at and in advance of the trail crossing. At a minimum, each
crossing should have pedestrian/bicyclist warning signs (B) and a crosswalk (A) installed at the location
of the trail crossing, and advanced pedestrian/bicyclist crossing warning signs (C). The advanced
pedestrian warning signage should be installed 200 ft. from all of the seven D&H Rail Trail crossings. See
figure below from the Empire State Trail design guide.

Figure III-3: Trail Crossing Components

On roadways with higher vehicle volumes, or where drivers regularly fail to yield at the crossings,
additional measures, such as Rapid Rectangular Flashing Beacons (RRFB) should be installed at the
crossing to increase pedestrian and cyclist safety. Additionally, all pedestrian warning signs should be
made of retroreflective fluorescent yellow-green sign sheeting and should also include the
retroreflective sign post strip for enhanced visibility.

Page | 9

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

1. CR 24

This crossing currently includes some of the recommended signage, including pedestrian crossing signs
and advance warning signage, (only provided for southbound traffic). It is recommended that advance
warning signage be installed south of the crossing to alert northbound traffic of the crossing.

Due to the existing speeds on the roadway reportedly exceeding the posted speed limit, Rectangular
Rapid Flashing Beacons (RRFBs) should be installed at this location in addition to the standard
pedestrian-bicycle crossing signage. RRFBs are high-intensity flashing yellow beacons mounted on
standard pedestrian warning signs at
uncontrolled crosswalks, see Figure III-4 for an
installed example. These beacons are activated
by pedestrians pressing a button before
crossing. RRFB installations are cost-effective
and have been proven to significantly improve
motorist yield rates at marked crosswalks. The
beacons can be powered by either solar energy
or a connection to the electrical grid. For this
installation, two beacon assemblies should be
positioned on the west and east sides of CR 24, with flashing beacons installed on both sides of the posts
to provide coverage for each approach to the crosswalk.

During the evaluation of existing conditions, it was noted that both sides of the pavement have a slight
drop from the pavement edge to the trail surface, making the trail inaccessible to users with disabilities
and inconvenient for cyclists. To address this, a curb ramp should be installed across the full width of the
trail, providing a smooth transition from the trail to the roadway. To meet ADA compliance, the curb
ramp must include detectable warning strips (DWS) covering the entire width of the trail. This design will
improve accessibility for pedestrians and cyclists, ensuring a seamless transition between the roadway
and the trail. For specific signage requirements at each crossing, refer to Table III-2.

The crosswalk is currently oriented at an angle across the roadway. The crossing distance is 75 ft. and
prolongs pedestrian exposure to traffic. It is recommended that the crosswalk be reconfigured so that
the crossing is perpendicular to the roadway, which will reduce the crossing distance to 26 ft. and
therefore, reduce the time to cross the road.

2. Main Street
Figure III-3: RRFB Installation

The Main Street crossing appears to have been recently
constructed, featuring a painted crosswalk and ADA-compliant
curb ramps equipped with detectable warning strips. Proper
signage is also in place to warn motorists of the crossing.
Advance warning signage should be installed 200 ft. prior to
the crossing in each direction. For specific signage
requirements at each crossing, refer to Table III-2.

Figure III-5: Main St Crossing

Page | 10

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

3. Water Street, Morrison Ave, E. Potter Avenue
Water Street, Morrison Avenue, and E. Potter Avenue are all low-volume local roads used primarily for
residential traffic. Each crossing has faded or missing crosswalks and missing signage. The crosswalks at
each location should be repainted using the “NYSDOT Type LS” design (the same type as installed at the
Main St. crossing), which includes parallel stripes and ladder bars for enhanced visibility. The pavement
markings should be applied with epoxy paint containing glass beads for retro-reflectivity or retro-
reflective thermoplastic to ensure long-term durability and improved visibility, particularly at night.

In addition, a concrete slab similar to one described on CR 24 equipped with detectable warning strips
should be installed at all three crossings to meet ADA compliance. Each crossing must be marked with
signage on both approaches to the crosswalk, clearly indicating that pedestrians and cyclists may be
crossing the roadway in this location. Each post should have signage on both the front and back,
providing left and right crosswalk markings from the driver’s perspective. For details on recommended
signage at each crossing, refer to Table III-2.

4. Church Street
Church Street was identified as having the highest AADT among all the evaluated crossings with 2,997
vehicles per day. The current crossing features a
recently painted crosswalk with grass approaches on
both sides. However, these grass approaches exhibit
an elevation difference between the trail and the
edge of the pavement, making the crossing
inaccessible for users with disabilities and
inconvenient for cyclists. To address this issue, a curb
ramp matching the width of the trail should be
installed, with detectable warning strips spanning the
full width of the trail. This will provide a smooth
transition from the trail to the roadway while
ensuring compliance with ADA standards.

Additionally, the crosswalk is currently oriented at an
angle across the roadway, creating an 80 ft. crossing
distance and prolonging pedestrian exposure to
traffic. It is recommended that the crosswalk be
reconfigured so that the crossing is perpendicular to
the roadway, reducing the crossing distance to 30 ft.
and reducing the crossing time by more than 50%.
Reconfiguring the crossing to achieve a perpendicular alignment would likely necessitate minor property
acquisition to accommodate the trail adjustment.

The crossing currently includes warning signs on one side of each post. Signage should be added so it is
present on both sides of the posts, ensuring visibility from both directions of the crossing. Finally,
advance warning signage should be installed 200 ft. in advance of the crossing. See Table III-2 for details
on recommended signage. Additionally, due to the higher traffic volume, Rectangular Rapid Flashing
Beacons (RRFBs) should be installed to enhance driver awareness of the crossing location.

Figure III-6: Church St Crossing

Page | 11

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

5. Andrews Lane
Andrews Lane is a low volume gravel roadway, utilized by local traffic only. The crossing currently lacks
warning signs for drivers and does not have a painted crosswalk due to the gravel surface. This
evaluation identified an elevation change between the roadway and the trail, making the crossing
inaccessible to users with disabilities. It is recommended that this crossing be re-graded by adding
material to create an ADA compliant slope up to the roadway surface on both sides. A concrete curb
ramp with DWS should also be added at the crossing. The surface material of this slope should match
the existing trail surface to maintain consistency. Additionally, signage indicating the trail crossing from
both directions should be installed. See Table III-2 for detail on recommended signage.

Recommended Trail Crossing Signage􀀃
Intersecting􀀃
Street􀀃Sign􀀃
Posts􀀃
Trail Crossing􀀃
W11􀀃15􀀃W16-7p(Bike/􀀃(Arrow)􀀃Ped)􀀃
Advance Warning􀀃
W11􀀃15􀀃W11􀀃15pSign􀀃(Bike/􀀃(Trail X-Posts􀀃Ped)􀀃ing)􀀃
W16-9p􀀃
(Ahead)􀀃
North Street􀀃
Main Street􀀃
Water Street􀀃
Morrison Ave􀀃
Church Street􀀃
E Potter Ave􀀃
Andrews lane􀀃
0􀀃
2􀀃
1􀀃
0􀀃
0􀀃
0􀀃
2􀀃
2􀀃2􀀃
0􀀃0􀀃
3􀀃3􀀃
2􀀃2􀀃
2􀀃2􀀃
2􀀃2􀀃
4􀀃4􀀃
0􀀃0􀀃0􀀃
0􀀃0􀀃0􀀃
0􀀃0􀀃0􀀃
1􀀃1􀀃1􀀃
0􀀃0􀀃0􀀃
2􀀃2􀀃2􀀃
0􀀃0􀀃0􀀃
0􀀃
0􀀃
0􀀃
1􀀃
0􀀃
2􀀃
0􀀃

Table III-2- Recommended Crossing Signage

Page | 12

FINAL Technical Memorandum
Village of Granville D&H Rail Trail
Crossings and Resurfacing Recommendations

6. Cost Estimate
The total cost to implement the aforementioned improvements at each roadway crossing is shown in
the table below. A full breakdown by roadway crossing and improvements is included in Appendix 2, if
the Village wishes to make these recommended improvements incrementally.

Village of Granville – D&H Rail Trail
Road Crossing Improvements
Cost Estimate
Items of Work / Road Crossing Itemized
Total
SIGNS $ 10,500
STRIPING $ 10,500
ADA RAMPS / CONCRETE LANDING $ 60,000
RRFB’S $ 50,000
TRAIL APPROACH (Trail material, grading) $ 21,000
MISCELLANEOUS $ –
WORK ZONE TRAFFIC CONTROL $ 15,200
ITEMIZED CONSTRUCTION SUBTOTAL: $ 152,000
FIELD CHANGE ORDER (5%) $ 7,600
MOBILIZATION (USE 4%) $ 6,800
CONTINGENCY / RISK (20%) $ 30,400
PRIVATE CONTRACTOR SUBTOTAL: $ 196,800
ENGINEERING / APPROVALS $ 40,000
CONSTRUCTION INSPECTION $ 30,000
FEDERAL-AID PROJECT COSTS: $ 266,800

Table III-3: Roadway Crossing Improvement Cost Estimate

Page | 13

Granville CR 24 Complete Streets Feasibility Study — DRAFT

DRAFT Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

Memo To: Mr. Jack Mance, Senior Transportation Planner Date: February 21, 2025
Adirondack/Glens Falls Transportation Council

From: Barton & Loguidice, D.P.C. (B&L) File: 1896.011.001

I. Introduction & Goals
On behalf of the Village of Granville and Washington County, the Adirondack/Glens Falls Transportation
Council (A/GFTC) and Barton & Loguidice, DPC (B&L), have prepared this Technical Memorandum to
evaluate potential complete streets improvements along County Route 24 (CR 24) from Riverside Drive
to East Main Street. This segment of CR 24 is frequently used by pedestrians and cyclists; however, it
currently lacks dedicated facilities to accommodate these users. Washington County DPW is planning a
pavement rehabilitation project for this corridor and expressed an interest to include potential complete
streets improvements, if feasible, prior to the construction of the rehabilitation project. The report
provides a comprehensive overview of existing conditions and evaluates potential complete streets
solutions.

Figure I-1:Project Location
Source: Google Earth

Page | 1

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

II. Existing Conditions
This section provides an overview of the current conditions along County Route 24 that may impact the
design and construction of complete streets amenities. It is intended to inform the evaluation of
conceptual alternatives and should not be considered a substitute for detailed engineering design and
land survey. Using the mobile application ArcGIS Survey 123, B&L staff collected data on the existing
conditions within the CR 24 corridor. Data collected includes photos, GPS coordinates, roadway
measurements, existing sidewalk conditions, distance from pavement edge to an obstruction, signage,
and culvert conditions. The segment of CR 24 under consideration for a complete streets assessment is
primarily lined by residential properties and a few small businesses. In this stretch, the land use
transitions from a predominantly neighborhood-scale residential context to a more rural and agricultural
setting. This rural character gradually evolves into an urban environment as the roadway approaches
East Main Street.

A. Roadway Characteristics
CR 24 is classified as a Rural Minor Collector with an annual
average daily traffic (AADT) of 2,403 vehicles per day and an 85th
percentile speed of 38 mph, as documented by the NYSDOT
Traffic Data Viewer. The NYSDOT traffic and speed data were
collected near the Village line, approximately where the D&H Rail
Trail crosses CR 24. This area is more urban in setting with curbing
and buildings close to the road. North of where the data was
collected, the speed limits changes from 30mph to 35mph, and
traffic speeds likely similarly increase through the more rural
setting. The travel lanes are approximately 11 ft. wide, while
shoulder widths vary between 0 and 4 ft. Currently, the corridor
lacks designated bike lanes and appropriate signage to support
bicycles and most of the corridor does not include sidewalks to
accommodate pedestrians. For detailed measurements and
further information, please refer to Appendix 1.

B. Roadside Conditions
Figure II-1 – CR 24 Roadway
The roadside conditions along CR 24 vary significantly.
Drainage infrastructure is unevenly distributed; open ditches
are present intermittently, such as between some driveways,
but are notably absent in several adjacent areas. Many
private driveways are equipped with drainage pipes beneath
them to convey the stormwater to the ditches. The field
observations documented the existing conditions within 15 ft.
of the pavement edge on both sides of the roadway. The
identified constraints include 60 utility poles, 15 trees, 13
locations with ditches, and 1 culvert running perpendicular to
the roadway. In total, 69 physical constraints were recorded
on the East side of the roadway, while 37 were found on the

Figure II-2 Utility pole adjacent to CR 24
Page | 2

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

West side of the roadway. The majority of the utility poles were located along the East side of the
roadway. Detailed information on these roadside conditions can be found in Appendix 1.

C. Existing Sidewalks
Sidewalks are present along the west side of CR 24 between
the intersection with E. Main St. in Granville and 63 North St.
(CR 24), and on the east side from E. Main St. to 28 North St.
The length of sidewalk on the west side is approximately 2,000
ft. long, and 900 ft. long on the east side. Additionally,
sidewalks are present at the north end of the project limits
from Chapmans General Store to 1330 North St. (CR 24), a
length of approximately 2,000 ft. All of the existing segments
were assessed for compliance with the Americans with
Disabilities Act (ADA) and evaluated based on several key
criteria: missing panels, panel heaving, obstructions, and width.
This study also evaluated the 1.3 miles of CR 24 roadway
between 63 North St. and 1330 North St. for the addition of
pedestrian facilities.

Each existing sidewalk segment was analyzed individually, typically representing one block, unless
interrupted by significant features such as large commercial driveways or unusually lengthy segments.
The assessment revealed that, out of the eight locations surveyed, seven segments were rated as
partially accessible or not accessible resulting in non-compliant conditions with ADA standards. The
most common deficiency included heaving panels which were found in all but one segment, followed by
missing panels which were found in five segments. The segment of sidewalk from E. Main St to 13 North
St. was rated as mostly accessible, the only segment in the study corridor. Detailed ADA compliance
findings, including specific issues identified and ratings, are provided in Appendix 1.

D. Signage
The existing signage along CR 24 was documented, including details on sign type, location, and proximity
to the roadway edge. A total of 13 signs were recorded along the corridor, with their distances from the
edge of the roadway ranging from 4 to 10 ft. For a detailed breakdown of signage types and their
locations, refer to Appendix 1.

Figure II-3-Existing Sidewalk

Page | 3

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

E. Pedestrian Crossings
The survey identified five pedestrian crossings. Two of these
crossings are marked with painted crosswalks: one at the D&H Trail
Crossing and the other at the intersection of North St. and E. Main
St. Both crosswalks were observed to be in good condition, with no
visible fading. Additionally, pedestrian crossing signage is present at
both locations to alert oncoming motorist of the crossing location.
One advance warning sign was documented North of the D&H Trail
crossing. The intersection located at North St. and E. Main St. was
the only location equipped with an ADA-compliant curb ramp,
including a detectable warning unit, which was only present on one Figure II-4 Crosswalk on CR 24 and

Main St.

side of the crosswalk. Please refer to Appendix 1 for further details.

F. Right of Way
The right-of-way (ROW) is a critical factor when evaluating the feasibility of pedestrian facilities along
the corridor. It dictates the available space for constructing sidewalks, multi-use paths, or other
infrastructure without encroaching on private property. Adequate ROW ensures that such facilities can
be integrated into the existing transportation network while minimizing the need for costly land
acquisition or reconfiguration of adjacent land uses. It is important to highlight that Washington
County’s GIS Web Map Parcel Viewer is developed through available tax mapping and is not a substitute
for detailed property boundary surveys. There were some inconsistencies found in the parcel viewer,
most notably showing sections where the roadway appears to extend beyond the ROW boundary on the
east side. Despite these discrepancies, the average ROW width was estimated to be 53.5 ft. from the site
review of utility locations and a comparison to the tax mapping boundary corridor. The average distance
from the edge of pavement to the edge of the ROW is estimated to be approximately 15 ft. on the east
side and 10 ft. on the west side.

III. Complete Streets Improvement Options
This section introduces four alternative concepts for improving pedestrian and bicyclist accommodations
along CR 24. These alternatives are intended to address current deficiencies in non-motorized user
safety and connectivity. Each concept will be evaluated for its effectiveness, constructability, and
potential impacts on existing infrastructure and traffic operations.

A. Sidewalk – Preferred Alternative
The first alternative involves maintaining the existing
roadway and shoulder dimensions while constructing
a sidewalk along the west side of the corridor. The
recommended sidewalk width is 5 ft., with a grass
buffer space between the edge of the pavement and
the sidewalk ranging from 4 to 5 ft. This buffer would
provide space for snow storage, leaf collection,
utilities, and transitions in grade where necessary.
The existing paved shoulder would remain along the

Figure III-1 – Typical Pedestrian Path without curb
Source: FHWA
Page | 4

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

roadway, preserving the current conditions for vehicular traffic.

This alternative would require coordination with all landowners along the corridor. Although the
proposed sidewalk and buffer space width would generally fit within the existing right-of-way in most
areas, construction easements would be necessary for grading and drainage work. Utility poles and
mailboxes would need to be relocated, and a limited number of trees would need to be removed to
accommodate the design. The existing shoulder (varying width between 0 and 4 ft.) does not meet the
requirements to accommodate cyclists, therefore this would be a pedestrian only improvement.

1. Repair Existing Sidewalk
a) Sidewalk Repair from W. Main St. to approx. 63 North St. (CR 24)
The sidewalk segment from 63 North St. to 13 North St. has been rated as
“Not Accessible” due to its narrow width, cracked, and missing panels. The
current conditions necessitate a full replacement with a new 5 ft. wide
sidewalk to meet ADA standards. The west side of CR 24 from 13 North St.
to East Main St. includes a 4 ft. wide sidewalk that widens to over 5 ft. as
it nears E. Main St. A driveway between south of 5 Main St. shows signs of
deterioration at the sidewalk crossing, with uneven pavement, creating
obstacles for individuals with disabilities. Similar conditions were
observed at the driveway of the Veterans of Foreign Wars eatery. This
segment of the sidewalk is rated as “Partially Accessible” as outside of the
noted deficiencies, it is in relatively good shape. The segment from 28
North St. to E. Main St. on the east side of CR 24 has been rated as “Not
Accessible” due to minor deficiencies within the sidewalk concrete and
utility poles placed in the middle of the sidewalk that restrict the sidewalk
width to less than 4 ft. North of 28 North St., the sidewalk diverges onto
Pine St. The 900 ft. segment of sidewalk on the east side of CR 24 from E.
Main St. to 28 North St. should be replaced with a new 5 ft. sidewalk, and the utility poles should be
relocated to behind the new sidewalk to meet ADA requirements. On the west side of CR 24, the 300 ft.
segment between E. Main St. and 13 North St. should be spot repaired where panels are heaving,
uneven, exhibit large cracks, or where crossings of driveways are not flush with the pavement. North of
13 North St. (CR 24) the entire sidewalk and curb should be replaced, approximately 1,650 ft. Ideally a 45
ft. snow storage buffer would be provided between the sidewalk and the curb. However, there does
not appear to be adequate width to accommodate this buffer due to roadside features such as retaining
walls, buildings, and the existing topography behind the existing sidewalk.

Figure III-2: 13 North St. to E.
Main St.

Page | 5

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

b) From Approx. 1330 CR 24 to Chapman’s General Store
The existing 4-foot-wide sidewalk is located on the west side of the
roadway only and exhibits several deficiencies, including panel
heaving or missing sections, surface deterioration, and overgrown
vegetation. Given the extent of these issues, a complete
reconstruction of the sidewalk is necessary. This includes
excavation and replacement of the approximately 2,000 ft. of 5 ft.
sidewalk, with integrated curb ramps and detectable warning strips
at intersections. Reconstruction would not require additional rightof-
way acquisitions, as the new sidewalk would be installed in the
same location as the existing sidewalk. Minor trimming of
overgrown vegetation, including tree branches, may also be

Figure III-3: Existing Sidewalk near Cove

required.

Lane intersection

2. Extend New Sidewalk
a) To Amazon Warehouse located at 1159 CR 24
Extending the CR 24 sidewalk North from 63 North St. to the Amazon Warehouse would require the
construction of approximately 2,700 ft. (0.5 miles) of new sidewalk on the west side of CR 24. This
section passes through predominantly open land, providing sufficient space for the sidewalk
construction. However, the installation may necessitate the relocation of 1-2 utility poles, signs,
mailboxes, and the removal of vegetation to clear the right-of-way for the proposed sidewalk. The
property at 1147 CR 24 poses a challenge due to the presence of trees and shrubs encroaching into the
right-of-way. However, the sidewalk could be constructed next to the vegetation and still maintain the
desired buffer between the pavement edge and the sidewalk. The ROW boundary obtained from the
county GIS database does not appear to be completely accurate but appears to be approximately 10 ft.
or more from the edge of pavement. It is likely a few ROW takings will be required to install the new
sidewalk. The sidewalk should include a buffer of 4-5 ft. from the edge of the existing pavement. The
sidewalk should be installed flush with the existing ground, eliminating the need for curb and drainage
installation. There is also a stream running under CR 24 through a culvert that will necessitate the
extension of this culvert. Some of the obstructions noted, such as mailboxes and utility poles, on the
west side of the roadway will be able to remain as they would be within the buffer between the edge of
the pavement and the sidewalk.

b) From Amazon Warehouse to 1330 CR 24
Constructing a sidewalk connection from the Amazon Warehouse North to 1330 CR 24 will require
approximately 4,250 ft. (0.8 miles) of new sidewalk construction on the west side of the roadway. The
new 5 ft. wide sidewalk should be installed 4-5 ft. from the edge of the existing pavement and be flush
with the existing ground so no curb or drainage improvements are needed. 6-7 utility poles along the
will need to be relocated to be between the buffer between the sidewalk and the roadway, or relocated
to be behind the new sidewalk. Additionally, many trees will need to be cut or avoided with a smaller
buffer space between the sidewalk and the edge of pavement. Other items such as stone walls,
mailboxes, signs, and timber fencing will need to be relocated. Similar to the previous section of CR 24,
the ROW boundary obtained from the county GIS database does not appear to be completely accurate
but appears to be approximately 10 ft. or more from the edge of pavement. It is likely a few minor rightof-
way acquisitions will be required to construct the new sidewalk.

Page | 6

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

Cost estimates for the aforementioned sidewalk repair and sidewalk extension work is shown in the
table below. The costs are broken into the previously discussed segments, and then further separated
by the cost of each general item of proposed work. The overall costs are separated into three categories,
an itemized construction subtotal, followed by additional costs if a private contractor were to perform
the work, and a total cost if federal aid were received. The itemized construction subtotal assumes that
the project sponsor could perform this work with their crews for this approximate cost, including
materials and labor. The federal-aid cost includes all of the necessary construction costs, and the
additional engineering/permitting and construction inspection costs to meet the federal aid contract
requirements and approvals.

County Route 24 Pedestrian Safety Improvements
Preliminary Cost Estimate
CONSTRUCTION ITEMS:
Main St. to 13
North St.
(West)
13 North St.
to 63 North
St. (West)
Main St. to 28
North St.
(East)
1330 North St.
to Chapmans
General
Store
63 North St.
to Amazon
Amazon to
1330 North St.
SIDEWALK $ 35,000 $ 352,000 $ 203,000 $ 241,000 $ 316,000 $ 483,000
DRIVEWAYS & ROAD CROSSINGS $ -$ 17,000 $ 11,000 $ 23,000 $ 27,000 $ 66,000
DRAINAGE $ -$ -$ -$ -$ 25,000 $ –
SIGNING & STRIPING $ -$ -$ 2,000 $ 2,000 $ 12,000 $ 8,000
MISC. RELOCATIONS $ -$ -$ 5,000 $ -$ 10,000 $ 20,000
CLEARING/TRIMMING/GRUBBING $ -$ -$ -$ -$ 15,000 $ 40,000
WORK ZONE TRAFFIC CONTROL $ 4,000 $ 37,000 $ 23,000 $ 27,000 $ 41,000 $ 62,000
ITEMIZED CONSTRUCTION SUBTOTAL: $ 39,000 $ 406,000 $ 244,000 $ 293,000 $ 446,000 $ 679,000
FIELD CHANGE ORDER (5%) $ 1,950 $ 20,300 $ 12,200 $ 14,650 $ 22,300 $ 33,950
MOBILIZATION (USE 4%) $ 1,700 $ 17,100 $ 10,300 $ 12,400 $ 18,800 $ 28,600
CONTINGENCY / RISK (20%) $ 7,800 $ 81,200 $ 48,800 $ 58,600 $ 89,200 $ 135,800
PRIVATE CONTRACTOR SUBTOTAL: $ 51,000 $ 525,000 $ 316,000 $ 379,000 $ 577,000 $ 878,000
ENGINEERING / APPROVALS $ 10,200 $ 105,000 $ 63,200 $ 75,800 $ 115,400 $ 175,600
CONSTRUCTION INSPECTION $ 6,120 $ 63,000 $ 37,920 $ 45,480 $ 69,240 $ 105,360
FEDERAL-AID PROJECT COSTS: $ 67,400 $ 693,000 $ 417,200 $ 500,300 $ 761,700 $ 1,159,000

Table III-1: Preliminary Cost Estimate

As the addition of sidewalks to CR24 does not address the needs of cyclists that wish to access the
Amazon Warehouse, they will be encouraged to use the adjacent D&H Rail Trail to the north of CR 24. A
potential access point from CR 24 to the rail trail is located at the driveway to the St. Peter & Paul
Cemetery. The driveway is installed between two commercial properties, one being the Slate Valley
Lanes Bowling Alley, and the other is a small apartment complex. This access location is less than 200 ft.
from the driveway access to the Amazon warehouse facility and would provide convenient access to the
facility from the D&H Rail Trail. A mid-block crossing consisting of signage, striping, and Rapid
Rectangular Flashing beacons should be installed at the mid-block crossing. The shoulder of CR 24
should also be widened between the driveway and the crossing to provide room for pedestrians and
bicyclists to walk on the side of the roadway. This mid-block crossing is anticipated to cost
approximately $35,000. See figure below.

Page | 7

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

Figure III-4: D&H Rail Trail to Amazon Warehouse Connection Option

B. Additional Options Not Progressed
1. Bike Lane
This alternative proposes the construction of
four to five-foot-wide bike lanes on both sides
of the roadway, in addition to the sidewalk
outlined in the sidewalk alternative. This would
involve widening the existing shoulders on both
sides of the roadway by two to four ft. The bike lanes Figure III-5-Typical Pedestrian Path Plus Bikeway-

Source: Empire State Design Guide

would be clearly delineated with standard pavement
markings and signage, installed per details and notes provided on NYSDOT Standard Sheet 685-01 to
ensure proper compliance with safety regulations. This alternative is fundamentally similar to a widened
shoulder option; however, it incorporates dedicated striping specifically designed for cyclists.

This alternative provides the benefits of the sidewalk alternative while offering dedicated facilities for
cyclists along both sides of the roadway.

Page | 8

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

The implementation of this alternative may require the relocation of a limited number of utility poles on
the east side to accommodate the wider pavement. Additionally, on the west side, the roadway
expansion presents the same obstacles outlined in the sidewalk alternative with the possibility of
additional tree removals, depending on the final alignment and grading requirements.

2. Shared Use Trail (Multi-Use Trail)
A shared use path (also known as a multi-use
path or side path) is an 8-12 ft. path designed
for use by both cyclists and pedestrians along
the east side of the roadway, as shown in
Figure II-5. By providing a paved asphalt facility
separate from non-motorized traffic, shared
use paths create a low-stress experience and
comfortable environment for users of every
age and ability. A 2 ft. shoulder/clear zone is
recommended on either side of the path to
facilitate drainage and user safety; however,
this may be reduced in constrained
environments. In addition, the minimum
recommended separation from the roadway is
5 ft.

Figure III-6 -Typical Shared Use Path configuration
Source: FHWA
This alternative would require the relocation of numerous utility poles to create the necessary space for
the construction of a multi-use trail, as a minimum of 2 ft. between a utility pole and trail edge is
required. The presence of a cattle farm on the east side of the roadway introduces an important
consideration: the frequent crossing of heavy equipment over the path could significantly accelerate its
deterioration over time and could pose safety concerns to users with the frequent vehicle traffic across
the trail. The impact of such equipment on the path’s surface should be carefully assessed to prevent
long-term damage. Additionally, this option would involve the largest right-of-way acquisition on one
side of the roadway, likely requiring multiple property acquisitions from adjacent landowners.

3. Shared Roadway
The shared roadway alternative
involves a design where travel lanes are
shared between motorists and cyclists,
while a sidewalk is installed as outlined
in the sidewalk alternative. This option
maintains the existing roadway

Figure III-7: Shared Roadway

configuration but includes signage designating the road

Source: Empire State Trail Guide

as a shared roadway, along with pavement markings to
alert motorists of the potential presence of cyclists. This alternative is suitable for roadways with an
AADT volume below 6,000 vehicles per day and an operating speed under 35 mph. Due to the 85th
percentile speed of 38 mph near the village line, and likely higher speeds to the north, the shared
roadway alternative is not recommended for CR 24.

Page | 9

FINAL Technical Memorandum
Village of Granville Trail Connections Analysis
CR 24 (North Street) Complete Streets

Discussions with the project advisory committee, consisting of representatives from the Town and
Village of Granville, AGFTC, and B&L were held on 10/30/2024 and 1/31/2025. These discussions
indicated that separate pedestrian facilities (sidewalks) are desired along the entire stretch of CR 24
within the project limits. Bicycle accommodations along this stretch of roadway are not feasible due to
the speed present within the corridor and the existing obstacles such as a meandering ROW and
obstructions such as trees and numerous utility poles. Bicyclists that wish to ride within this corridor will
be directed to use the adjacent D&H Rail Trail, which runs parallel to this corridor.

Page | 10

DRAFT Argyle Pedestrian Improvement Plan

The text below has been provided to facilitate screen reader technology. For the full report including tables and graphics, please refer to the .pdf version by clicking the icon to the right.

 

Argyle Pedestrian Improvement Plan

DRAFT August 2024

I. Project Background, History, and Goals
Over the course of the last few years there have been several efforts to identify potential improvements to the pedestrian facilities in and around the Village of Argyle. In particular, two in-depth planning efforts were undertaken; the 2018 Argyle Pedestrian Network Extension Study, which examined potential connections to the Dollar General, and the 2022 Argyle Sidewalk Assessment conducted by the Argyle Improvement Association.
This plan intends to incorporate and build upon these previous efforts by developing concepts, streetscape typologies, and cost estimates for pedestrian amenities in and around the Village.
II. Project Area and Jurisdiction
The study area includes most of the Village of Argyle as well as portions of the surrounding Town. See Figure 1 for study area boundaries. Within the study area, Main Street (NYS 197 & NYS 40) and Sheridan Street (NYS 40) are under the jurisdiction of NYS Department of Transportation (NYSDOT). In terms of County Roads, Washington County has jurisdiction over County Route 47. All other roads within the study area are Village-owned.
A. Maintenance Responsibility
Under NYS Highway Law, the maintenance of sidewalks along State routes is the responsibility of the local municipality. This includes both corrective and preventative maintenance. Although NYSDOT may choose to construct or repair sidewalks, in most cases municipalities elect to undertake sidewalk projects on their own by seeking grant funding. Historically, as long as the facilities meet applicable State design standards, NYSDOT is usually amenable to grant the necessary work permits and may also provide limited technical assistance or project coordination in certain cases.
During the course of “pavement alteration” projects on State highways, NYSDOT is required to make any necessary repairs or upgrades to existing curb ramps which are located along the roadway to bring such facilities into compliance with ADA guidelines. It is anticipated that the next round of pavement preservation undertaken by NYSDOT within the Village (currently slated for the 2024 construction season) will include a number of improvements to curb ramps as well as the introduction of marked crosswalks. These locations have been integrated into the concepts proposed in section IV of this document.

B. Pedestrian Infrastructure Condition
In July 2023, staff from the Lake Champlain-Lake George Regional Planning Board assessed existing pedestrian infrastructure to determine accessibility according to the standards of the Americans with Disabilities Act (ADA). Sidewalks and curb ramps were rated as Not Accessible, Less Accessible, More Accessible, and Fully Accessible according to criteria used by NYSDOT. This data was collected using a GIS smartphone app developed by Warren County GIS staff.
The results of the assessment can be seen in Table 1

Table 1 – ADA Statistics, Sidewalks and Curb Ramps*
1 – Not Accessible: 0.56 miles of sidewalk
1 – Not Accessible: 9 curb ramps
2 – Less Accessible: 0.31 miles of sidewalk
2 – Less Accessible: 8 curb ramps
3 – More Accessible: 1.04 miles of sidewalk
3 – More Accessible: 2 curb ramps
4 – Fully Accessible: 0.02 miles of sidewalk
4 – Fully Accessible: 0 curb ramps
*As of 2023 there were no marked crosswalks in the study area.

C. Roadway Characteristics
The state highways within the study area have varying shoulder widths. In some areas, wide shoulders are used for on-street parking. In certain places, especially near the funeral home, the current roadway striping is insufficient to accommodate demand for on-street parking. Curbing is present in some locations but is inconsistent. Public outreach indicates that drainage is an issue, especially in areas where curbing is insufficient.
County Route 47 is a two-lane marked highway with narrow shoulders. Although vehicles frequently park along the grassy shoulder for events at the American Legion, there is no designated on-street parking. There are no curbs along this roadway.
The Village-owned streets are narrow, unmarked roadways. Curbing is inconsistent, leading to significant drainage issues during storm events. Some residents and visitors park on the grassy area between the sidewalk and road, which can lead to degraded vegetation, rutted turf, and occasional blockages of the pedestrian facilities.
1. AADT and Speed
Traffic volume, as expressed in Average Annual Daily Traffic (AADT), is listed in Table 2 below. Traffic counts are conducted by NYSDOT on a periodic basis for all State-owned and federal-aid eligible roadways as well as a sampling of local roads. The % of truck traffic has also been included for reference.
In terms of vehicle speed, data was collected for the Argyle Sidewalk Extension Study in 2018, with additional data collected in 2024 for this study by the consultant team at Creighton Manning, a GAI Company. All locations were within the 30 MPH posted speed limit.
It is worth noting that all speed data collected indicated that the 85th percentile speed (i.e., the speed at which 85% of drivers drive at or below) was above the posted 30 MPH speed limit. Although vehicle speed did not appear to play a significant factor in the crash data as reviewed in Section II.C.2, the consistent trend of vehicle speeds above the posted limit is a factor to be considered for pedestrian crossings and streetscape design.
2. Crash History
Crash statistics for the study area were accessed using NYSDOT’s CLEAR Safety tool. The most recent five years of data (03/31/2018 – 03/31/2023) were pulled to capture pre-pandemic conditions. In this period, 23 accidents occurred. In terms of severity, three involved injuries while the remaining 20 were property damage only. One of the noted injury crashes, located near 37 Sheridan Street, involved serious injury to a pedestrian.

III. Initial Public Input
After discussing multiple formats and options, the project steering committee elected to gather the initial round of public input via a paper survey and mapping exercise. This option was judged to be the most accessible to the community. Copies of the survey were distributed by members of the Argyle Improvement Association (AIA) at the Thistle Day event on Saturday, September 30, 2023. In addition, the survey was made available at the Argyle Free Library and the Post Office. The survey was closed on October 30, 2023.
A. Public Survey Results
Sixty-eight (68) surveys were completed, providing a thorough cross-section of residents and visitors to Argyle. In terms of the survey questions, 56% of respondents indicated that they regularly walk within the Village, while 76% said they would walk more often if the sidewalk conditions improved. The biggest concern regarding walking was safety.

In addition to the survey questions, respondents were invited to share their opinions regarding the locations of potential crosswalks as well as the replacement and/or installation of new sidewalks. The most desired locations for crosswalks included:
* Main Street/Sheridan Street (35 votes)
* Sheridan Street/East Street (25 votes including nearby votes for a crossing at the library)
* Main Street/Barkley Avenue/Post Office (25 votes split between a crossing at Barkley and a crossing at the Post Office)
* School/Firehouse (9 votes)
* Sheridan Street/CR 47 (8 votes)
In terms of the most desired locations for existing sidewalk repair or replacement, the most popular locations were Main Street from Sheridan Street to West Road and Sheridan Street from Main Street to just past East Street. New sidewalks were desired in the following locations:
* NYS 40 from Argyle Central School to Firehouse
* Sheridan Street between East Street and Argyle Central School
* Main Street from Sheridan Street to Dollar General
* East Street

In addition, respondents were given the opportunity to provide additional ideas or concerns. These responses included:
* I can’t use my skateboard
* Lots of people walk to Dollar General. A sidewalk and crosswalk would be awesome!
* Mud on “sidewalk” on s. side of Sheridan is like ice when wet. VERY BAD!!
* Difficult sidewalks make using a stroller impossible
* For exercise we choose to walk in rural areas/roads as opposed to the Village. Argyle Rec Field and the school offers walking for walkers.
* Dogs
* It is difficult to cross to the Post Office.
* Crossing Rt-40/Rt-197 is at the pedestrian’s peril; traffic in the village is too fast and there are no crosswalks.
* Drainage
* There is no safe way to cross the street to Dollar General!
* I would walk more if my street had a sidewalk. It is too dangerous to walk.
* Crosswalks near Stewarts would be very beneficial
* [Regarding the intersection of County Route 47 and State Route 40] Can we square this to a T so people coming off Route 40 are not going 65
* Sidewalks are rough
* Would walk if sidewalk were safer
* Walking our kids & dogs is difficult.
* How about sidewalk with curbs
* Protect the school kids
* I would like to see a crosswalk or two available to Argyle School students and pronounced sidewalks

B. Argyle Improvement Association November 2023 Meeting
The results of the public survey were presented to the AIA during the November 2023 meeting. After discussing the survey and initial delineation of Priority Locations and Streetscape Typologies (see Section IV), a number of additional suggestions were made. In addition, the discussion provided additional context regarding the history of pedestrian-related issues within the village. Specific topics of discussion included:
* Regarding the locally-owned streets, sidewalks were only ever installed on one side of the roadway. This may complicate efforts to install sidewalks along both sides of the street (as opposed to re-establishing sidewalks which once existed).
* Although West Road was not a major focus of the survey results, it should be included within potential streetscape typology areas (see Section IV).
* There is an existing Village access road that links the back of the Highway Department property on Route 40 to the Prospect Hill Cemetery, which is a popular place for locals to walk. This access road could potentially be used to create a loop for pedestrians, in conjunction with other improvements.
* The idea of creating a more direct pedestrian access to the Argyle Recreation Field was discussed. All agreed that improved pedestrian access was needed. Some felt that having additional entries could make it more difficult to keep track of children during large events and that one entryway was sufficient.
* The need for improved storm drainage and/or curbs was discussed, especially in areas where decades of road repaving have raised the elevation of the travel lanes. Ultimately this will require an engineering solution.
* Recent repaving and restriping on NYS 197 near the MB Kilmer Funeral Home has reduced the availability of on-street parking. Although the overall roadway width has not changed, the shoulder on the west side of the roadway has been reduced in width due to the placement of pavement markings. Vehicles still park along the shoulder in this location, but often encroach on the travel lane.
IV. Priority Locations and Streetscape Typologies
Using the results of the public survey and subsequent AIA input, Priority Locations and Streetscape Typology areas have been delineated. These can be seen in Figure 8.
Priority Locations refer to discrete intersections where crosswalks are desired. These concept plans should take into account traffic volume and speed, intersection stopping sight distance, streetscape elements such as trees and benches, pavement markings, lighting, and signage as appropriate. The locations shown in Figure 8 are approximate; see section IV.A for recommended crossing location details. In addition to the five crossing locations listed in Section III.A above, the crossing location at the Dollar General previously identified in the 2018 Argyle Sidewalk Extension Study is to be incorporated by reference.
Streetscape Typologies refer to roadway cross-sections which may include sidewalks, snow storage, curbing, on-street parking (if needed), streetscape elements such as trees and lighting, and travel lanes, as appropriate. The exact boundaries of the typology areas have not been designated; the boundaries in Figure 8 are approximate. The three typologies are:
* Village Core, which features higher-density mixed-use development, high traffic volumes, and on-street parking
* Village Connectors, which have lower-density mixed-use development, high traffic volumes, higher vehicle speeds, and limited on-street parking
* Neighborhood Streets, which feature higher-density residential development, low traffic volume and speed, and may integrate on-street parking or grass snow storage

A. Recommended Improvements
1. Pedestrian Crossing Concepts
Due to the potential for pedestrian/vehicle conflict, crosswalks are a critical component of a safe, comfortable pedestrian network. There are several factors which influence the design and location of pedestrian crossings. These include:
* Visibility. Good crossing locations will allow drivers to see pedestrians waiting to cross the street, to give vehicles enough time to yield properly. Visibility is often a combination of sufficient street lighting and signage as well as infrastructure design that allows for adequate sight distance so that pedestrians are not blocked by parked cars or other features.
* Sidewalk alignment. Many pedestrians seek the most efficient route of travel. As such, crosswalks should be aligned with existing sidewalks wherever possible to reduce the likelihood of pedestrians crossing at unmarked locations.
* Predictability. Through effective signage, drivers should be able to anticipate the potential for pedestrian activity, especially in mid-block locations.
* Crossing distance. Where possible, it is usually desirable to reduce or minimize the length of crosswalks to limit the potential for pedestrian exposure to vehicles. Shorter crossings are also more comfortable for those with mobility challenges. In locations with overly wide travel lanes and/or shoulders, crossing distance can be reduced through curb bump-outs. However, the tradeoff of curb bumpouts is reduced on-street parking and the potential for more complicated snow removal.
The following section of this report contains excerpts of concept plans for the recommended pedestrian crossings. For the full version of the drawings, see Appendix A.

 

a) Main St./Sheridan St.
The Main Street and Sheridan Street intersection forms the heart of the Village of Argyle. This location carries the most traffic within the Village and also provides access to a convenient store/gas station, restaurant, hardware store, and local bank branch. In addition, there is a vacant lot which is often used as a pull-off for freight truck drivers and area residents for pop-up farm stands.
Currently, this intersection does not feature any crosswalks, despite having sidewalks on all approaches. As such, many pedestrians cross at existing business driveways or wherever they happen to park their car on-street. This makes it difficult for drivers to anticipate predictable locations where pedestrian activity might occur.
The upcoming NYSDOT repaving includes the establishment of painted crosswalks and ADA accessible curb ramps on the east and south approaches to the intersection. In addition, this plan recommends the addition of a crosswalk and associated curb ramps on the north approach, as shown in Figure 9. The concept also includes the establishment of new curbing and sidewalks along the southeast corner of the intersection. This will define the edges of the existing vacant lot, which will improve access management and reduce the potential for pedestrian/vehicle conflicts while also improving the aesthetics of this important community node.
b) Barkley Ave/Town Hall/Main St. (NYS 40)
This section of Main Street is home to the Argyle Town Hall and a US Post Office, while Barkley Avenue provides access to the Argyle Presbyterian Church and the Community Garden. As such, there is a fair amount of pedestrian activity on this section of roadway, which was also noted as a priority area during the public survey. As part of the NYSDOT pavement project, a crosswalk and curb ramps will be added to Barkley Avenue.
Several alternatives for Main Street crossing locations were considered, including the north and south side of Barkley Avenue as well as a mid-block crossing at the Post Office. Ultimately, the north side of Barkley Avenue was selected based on factors such as sight lines, existing driveways, and the alignment with existing sidewalks. See Figure 10.
To improve the visibility of pedestrians, this concept also calls for the establishment of a “no parking” zone for approximately 20’ on either side of the crosswalk. This is a critical safety factor to ensure that parked cars do not block the visibility of pedestrians from drivers on the roadway. As an option to further increase visibility, an RRFB could be considered during detailed design, in coordination with NYSDOT.
c) Sheridan Street/Elm Street/Library
The East Street/Sheridan Street intersection provides access to the Argyle Free Library, an important community resource. The library has no off-street parking lot, making on-street parking a priority. The parking lane on the north side of Sheridan Street is wide and heavily sloped, which increases the crossing distance for pedestrians. In addition, there is no curb ramp; users with mobility challenges or pushing a stroller must use a nearby driveway to get access to the sidewalk. Other factors which influence the location of a crosswalk include existing street lighting on the southwest corner of the intersection, and the alignment of existing sidewalks along the west side of East Street.
To address these issues, the proposed concept plan includes creating a short pedestrian bump-out in front of 25 Sheridan Street with a crosswalk to align with the sidewalk on East Street (see Figure 11). This will result in displacing approximately 2 on-street parking spaces. However, two mitigations are proposed to make up for this impact. First, it is recommended that the on-street parking spaces should be delineated with pavement markings. This will result in more efficient utilization of the space that currently exists. In addition, the existing grassy buffer/maintenance strip to the east of the driveway at 25 Sheridan Street could be removed and replaced with on-street parking. This scenario maintains a meaningful amount of green space in front of the private residence while creating additional parking for the library.
d) Sheridan St./County Route 47
A crossing is proposed on the east leg of the three-way intersection of Sheridan Street and County Route 47, as shown in Figure 12. This location provides access to the proposed sidewalk to connect to the American Legion and Prospect Hill Cemetery. No crosswalk is currently proposed for County Route 47; however, if sidewalks are installed on the south side of Sheridan Street in the future, a crosswalk should be considered at that time.
e) Sheridan St./School/Fire Department
Establishing a connection between the school and Highway Department/Fire Department is a major priority for both residents and stakeholders. These facilities are heavily used by the community for a variety of events. For example, students walk to the Fire Department for field trips; the Fire Department is also the designated evacuation location for the school. In addition, there is a pedestrian connection between the rear of the Highway Department property and the Prospect Hill Cemetery.
GIven the existing sidewalks within the Argyle Central School property as well as sight distances, it is recommended that the crosswalk be located in front of the Highway Department. This would require the construction of an additional sidewalk/sidepath on the north side of the road to connect to the school as well as sidewalks on the south side of the road to connect to the Fire Department. (See Figure 13). As an option to further increase visibility, an RRFB could be considered during detailed design, in coordination with NYSDOT. Although not strictly pedestrian-related, other options to reduce driver speed (and thereby improve pedestrian safety) could include the installation of speed feedback signs and the establishment of a reduced speed school zone.

2. Streetscape Typologies
The elements of roadway design are contingent on a variety of factors including surrounding land use, vehicle speed, stormwater drainage, right-of-way width, and traffic volume. As such, not all streets are built the same.
To capture the character and context of the Village of Argyle, three streetscape typologies were developed. These represent generic idealized snapshots of the road network; for any given location, certain elements may need to be adapted to fit the available right-of-way. The design standards and guidance below were excerpted from NYSDOT Highway Design Manual, the AASHTO Guide for the Development of Bicycle Facilities, and the NACTO Urban Street Design Guide. The streetscape elements include:
* Travel Lanes. The minimum standard for travel lanes in most situations is 10’; wider lanes may be desirable to accommodate larger vehicles such as freight trucks or agricultural equipment. However, lane width is also correlated strongly with vehicle speed; in general, drivers will go faster as lane widths increase. In a village setting with a 30 mph speed limit, it is therefore recommended to keep lane widths below 12’.
* Parking Lanes/Shoulder. A 4’ shoulder is generally accepted as the minimum width to accommodate cyclists, while the minimum width for a parking lane is 7’. However, larger vehicles such as light-duty trucks may not fit comfortably into the minimum guidelines; 8-9’ shoulders would allow for a wider variety of vehicles to park on-street.
* Curb/Gutter. Curbs are used both to channel stormwater and to provide vertical separation for sidewalks. Gutters or mountable curbs allow for stormwater channelization while also protecting the integrity of the pavement edge somewhat against degradation from vehicle traversal.
* Grass Buffer. Also known as a maintenance strip, this is the linear area between the shoulder and the sidewalk. This buffers pedestrians from traffic, provides a place for utility poles and mail boxes, and allows for snow storage in the winter. This can be occupied by low vegetation/grass or it may be paved with concrete or decorative pavement. To maintain vegetation, a minimum width of 3’ is preferred with an outside range of 2-6’. If space is not available within the right-of-way, the buffer can be eliminated; however in that case it is recommended that 6” curbs be installed to separate the road edge from the sidewalk and sidewalk width should be increased to 6’, preferably 8’, to provide extra separation from the roadway.
* Sidewalks. The ADA minimum standard width in most cases is 5’, although this can be reduced to 4’ in specific circumstances. For areas with higher traffic volume and greater pedestrian activity, it is usually recommended to place sidewalks on both sides of the road.
Not all roads will feature all elements. A description of the streetscape typologies is included below.
a) Village Core
The Village Core represents the heart of the community where the majority of commercial and community events take place. These roadways feature the highest pedestrian and traffic volumes and have right-of-way widths varying from 55’-70’.
Currently, most of this area features ad-hoc on-street parking along the road shoulder. Over many decades, curbs have become degraded in many locations as the state highways have been repeatedly paved over, raising the height of the pavement. In addition, parking incursions have reduced the viability of much of the grass buffer area, to the point where the on-street parking “lane” now abuts the sidewalk.
The proposed roadway section (Alternative 1, see Figure 14) would restore the curb and re-establish a grass buffer between the sidewalk and on-street parking. Even accounting for sidewalk widening to bring the facilities into compliance with ADA standards, this design concept would result in an overall narrowing of the road profile in many locations, essentially allowing for additional space to be used for front yards. As an option where right-of-way does not allow for parking on both sides, Alternative 2 (see also Figure 14) would instead have a shoulder on one side. Although this shoulder is not wide enough to allow for parking, the use of mountable curbs or concrete gutters would accommodate the occasional delivery truck or emergency vehicle to pull on to the grass buffer while still maintaining the integrity of the pavement edge.

b) Village Connectors
The density of commercial and residential land uses in these areas is lower than the core; however, there are still important pedestrian connections to be maintained and enhanced. Currently, there are sidewalks only on one side of the road. On the other side, the road shoulder meets the adjoining land without curbs; stormwater is accommodated via swales or direct absorption.
Two alternatives are proposed, as shown in Figure 15. Alternative 1 calls for sidewalks on both sides, which would maximize pedestrian connectivity. However, given that historically sidewalks were never established on both sides, this would require the support of dozens of property owners to achieve, which could make this a long-term prospect for implementation. Alternative 2 calls for sidewalks on one side, which would still improve pedestrian conditions overall, especially if improved crosswalks are installed as called for elsewhere in this plan.

c) Neighborhood Streets
Elm Street, East Street, West Street, and Barkley Avenue are representative of the traditional residential land uses found in villages throughout the northeast US. Currently, these un-curbed streets feature narrow sidewalks on one side only with 9-10’ travel lanes. Some residents choose to park on-street, pulling the vehicle into the grass buffer between the street and the sidewalk (or on to the lawn, in cases where no sidewalk exists). As a result, the edge of pavement and grass is degraded in many locations. Alternative 1, seen in Figure 16, would replace and improve the existing elements of the roadway. This would include an ADA-compliant 5’ sidewalk as well as a grass buffer with a mountable curb or concrete gutter, which would allow the current occasional on-street parking to continue while maintaining the edge of pavement. Alternative 2 includes sidewalks on both sides of the roadway (see sidebar for additional information).

V. Implementation and Next Steps
A. Cost Estimates
The following cost estimate information was broken down into several categories to enable the Village to prioritize future project phasing. These include:
* Intersection improvements, which encapsulate the pedestrian crossing concepts recommended in this report
* Sidewalk replacement, to bring all existing sidewalks up to ADA standard and establish any other features recommended in the streetscape typologies such as curbing
* New sidewalk construction (high priority), to install new sidewalks in locations which were identified as a higher need from the public survey and mapping exercise
* New sidewalk construction (low priority), to install new sidewalks in locations which were identified as a lower need from the public survey and mapping exercise, but would still provide pedestrian connectivity overall
These have further been broken down into logical segments as seen in Table 4, so that the Village may “mix-and-match” the project into discrete phases as appropriate. It should be noted that these estimates were created with the assumption that federal funding would be utilized, which involves material sourcing guidelines, labor regulations, and project elements such as construction inspection. These factors may not be relevant if construction is undertaken without federal aid. However, in all cases, public pedestrian infrastructure must be designed and built according to the standards of the Americans with Disabilities Act, regardless of the funding source used.
Table 4: Argyle Pedestrian Plan Cost Estimate Summary
Intersection Improvements
Construction Cost
Total Project Cost
Main St./Barkley Ave. Improvements: $53,000 construction/$69,000 total cost
Sheridan St./East St. Improvements: $76,000 construction/$99,000 total cost
Sheridan St./Main St. Improvements: $117,000 construction/$153,000 total cost
Sheridan St./Route 47 Improvements: $35,000 construction/$46,000 total cost
Mid-Block Crossing at School: $61,000 construction/$80,000 total cost
Subtotal – Intersection Improvements: $342,000 construction/$447,000 total cost
Sidewalk Replacements
East Side of Main Street (Sheridan to West): $173,000 construction/$225,000 total cost
West Side of Main Street (Argyle Laundromat to West): $493,000 construction/$641,000 total cost
North Side of Sheridan St (Main to Argyle Central School): $291,000 construction/$379,000 total cost
South Side of Sheridan St (Main to East): $70,000 construction/$91,000 total cost
South Side of Elm St (Main to East): $70,000 construction/$91,000 total cost
South Side of West Rd (Main to 360′ west of intersection): $30,000 construction/$39,000 total cost
North Side of Barkley Ave (Main to Presbyterian Church): $45,000 construction/$59,000 total cost
South of Barkley Ave (320′ south of Barkley along parking lot): $43,000 construction/$56,000 total cost
Subtotal – Sidewalk Replacements: $1,215,000 construction/$1,581,000 total cost
New Sidewalk Construction (High Priority)
East Side of Main St (Sheridan to Dollar General): $181,000 construction/$236,000 total cost
South Side of Sheridan St (East to County RT 47): $94,000 construction/$123,000 total cost
North Side of County RT 47 (Sheridan to Cemetery): $125,000 construction/$163,000 total cost
North Side of Sheridan St (Argyle School to Highway Dept): $45,000 construction/$59,000 total cost
South Side of Sheridan St (Argyle Highway Dept to Fire Dept): $33,000 construction/$43,000 total cost
West side of East St (Elm to Barkley): $87,000 construction/$114,000 total cost
North Side of Barkley Ave (Presbyterian Church to East): $48,000 construction/$63,000 total cost
Subtotal – New Sidewalk Construction (High Priority): $613,000 construction/$801,000 total cost
New Sidewalk Construction (Low Priority)
South Side of Sheridan St (County Rt 47 to Argyle Highway Dept): $319,000 construction/$415,000 total cost
North Side of Elm St (Main to East): $117,000 construction/$153,000 total cost
East Side of East St. (Sheridan to Community Gardens): $257,000 construction/$335,000 total cost
Subtotal – New Sidewalk Construction (Low Priority): $693,000 construction/$903,000 total cost
Grand Total – All Improvements: $2,863,000 construction/$3,732,000 total cost

B. Funding
Although some communities opt to make incremental infrastructure improvements through annual budget expenditures, most municipalities seek grant funding to offset the cost of large-scale capital construction projects all at once. For additional information concerning project phasing options, see section V.C. below.
1. Federally Administered Funding Programs
There are a number of federal grant programs that can be used to design and construct sidewalks and related pedestrian infrastructure. Given that programs are introduced and retired on a regular basis, the most comprehensive and up-to-date list of federal funding programs can be accessed on the FHWA website. This list includes programs which are administered by NYSDOT or A/GFTC (see below for more information) as well as programs which are solicited directly by the Federal Highway Administration. Specific programs of note which are solicited directly through FHWA include Safe Streets 4 All (SS4A) and the Active Transportation Infrastructure Investment Program (ATIIP).
2. State and Locally Administered Funding Programs
A/GFTC Make the Connection: The intent of this program is to improve the non-motorized travel network in the A/GFTC region by addressing gaps or deficiencies that discourage or physically impede efficient and safe bicycle and pedestrian activities. The local match for this program is 20%; in-kind labor is not allowed as a match source. This program is limited to design-only for project sponsors without direct federal-aid experience. The next round of MTC is anticipated to be released in fall 2024 and is administered directly through A/GFTC.
Transportation Alternatives Program (TAP): This program is administered by NYSDOT every other year and allows for the design and construction of a wide variety of bicycle and pedestrian infrastructure. Project applicants must compete within their applicable NYSDOT Region, in this case Region 1 which also includes the greater Capital District. The minimum federal share for each project is $500,000; with a 20% match of $125,000, the resulting minimum total project cost is $625,000.
Carbon Reduction Program (CRP): CRP funds may be obligated for projects that support the reduction of transportation emissions, including facilities for pedestrians, bicyclists, and other nonmotorized forms of transportation. In the A/GFTC region, applicants can seek CRP funding two ways: a limited A/GFTC-only allocation which is solicited as part of the overall regional Transportation Improvement Program or co-solicited with the TAP program through NYSDOT every other year. For the combined NYSDOT TAP/CRP solicitation, the TAP project minimums apply. As this is a relatively new program, it is recommended that potential applicants seek guidance from A/GFTC and NYSDOT Region 1 prior to seeking funding.
C. Project Phasing/Partnerships
To undertake a project of this magnitude, it may be desirable to phase the project or to seek opportunities to bundle the sidewalk construction with other projects, or to work with partners to reduce the overall burden on the Village. Some options include:
* Bundle with sewer/water upgrades. The Village is already exploring a variety of options for water and sewer infrastructure. In some cases, these projects would require digging up some of the existing sidewalks anyway, which could provide a logical opportunity to replace them with better pedestrian facilities. There may also be ways to use multiple funding sources to reduce local match requirements for grants.
* Phase design first. One option would be to pursue design for sidewalk and pedestrian improvements as a stand-alone project. This could be self-funded or grants such as MTC could be used. The benefit of this approach is that having a completed design and accurate cost estimates is a valuable metric for certain funding applications such as TAP, since many of the potential unknowns of construction have already been identified.
* Phase high priority locations first. Another option would be to seek funding for the highest priority locations, while leaving lower priority areas for the future. This would reduce the short-term financial impact to the Village. However, given recent historical inflation trends, it is likely that the cost of sidewalk construction even a few years in the future will be more expensive. In addition, this approach creates multiple seasons of construction, which could be frustrating for residents and business owners.
* Incremental improvements. Like many municipalities in New York, the Village already has a policy which allows for cost-sharing with residents and property owners for sidewalk improvements at individual parcels. Although in theory this should result in the incremental improvement of sidewalks, in practice very few property owners actually utilize this program. In addition, it is likely that there will be at least a few property owners who are unwilling to participate, leading to inconsistent sidewalk conditions. If those locations were then improved at the Village’s expense in the future, this could lead to frustration and resentment of any property owners who did contribute to improvements in good faith. The other drawback to this approach is that the repeated mobilization of contractors for short segments of sidewalk construction can be more expensive on a unit basis than undertaking longer sections at the same time.
A related concept would be to form a sidewalk district which would collect a nominal fee from property owners on an annual basis, which could then be used to fund future sidewalk improvements. This option would likely take several years to result in enough funding to make meaningful improvements, but it would eliminate the potential inconsistency inherent in the current local law.
* Explore local fundraising options. The Village of Argyle is an active, engaged community. Groups such as the Argyle Improvement Association and the local American Legion could potentially lead a large-scale fundraising effort dedicated to sidewalk improvements. Although it is unlikely that this would result in enough funding to completely offset a match for construction, it may be feasible to use this funding as a match for a design-only project or for a smaller-scale construction effort.
* Consider partnerships with Town and/or County. Although the main focus of this plan is on Village infrastructure, there are concepts which would require the involvement of the Town of Argyle and Washington County to bring to fruition. A multi-jurisdictional approach could not only reduce the administrative and/or financial burden on the Village but would also result in a more competitive application for funding.
D. Maintenance
Maintenance of pedestrian infrastructure is a key concern for any municipality. For the purposes of this plan, “maintenance” includes short-term upkeep, such as removing leaves, snow, and debris, as well as long-term preservation of pavement, drainage, and general infrastructure condition to ensure ADA accessibility. This section is intended to provide a general overview of issues related to pedestrian infrastructure maintenance.
1. Short-term maintenance
In New York State, many municipalities have enacted local laws which delegate the removal of snow, leaves, and/or other debris to the adjoining landowner; Argyle sets forth these provisions in Local Law 1 of 2007. However, some landowners may not be physically capable, available, and/or willing to engage in timely snow removal. Argyle’s regulation levies a fine in the case of noncompliance within a set time period, in this case 48 hours after a snowfall. Although this may be effective in some cases, not all municipalities have the capacity to enforce these types of violations. Another option would be to purchase dedicated snow-removal equipment and have municipal employees undertake the snow removal throughout the Village as needed. Although this will increase overall accessibility in the Village, it is also more expensive.
2. Long-term maintenance
Regarding long-term maintenance, Argyle’s sidewalk regulations state that “The owner of premises abutting on any street
or road who owns the property where a sidewalk has been laid shall repair, maintain, replace and reconstruct such sidewalk.” However, no guidance is included regarding standards for maintenance and repair and there are no references to the ADA. This could create some confusion as there is no clear threshold established for when repair and replacement should take place. In addition, as stated above, many property owners choose not to repair or replace their sidewalks, even though the Village of Argyle currently has a policy which enables cost-sharing to offset the expense.

These types of local laws, although very common in NYS, can lead to legal confusion with regards to property owner liability for injury related to poor pavement condition (i.e. trip-and-fall lawsuits) versus municipal requirements to maintain ADA accessibility under federal law. In general, although these types of local laws may lead to some incremental advances, they do not ensure consistent sidewalk maintenance in the long term. The most effective way to ensure that accessible, safe sidewalks are available is for the Village to undertake the design, construction, and long-term maintenance of the pedestrian infrastructure network.

Ultimately, the ADA states that municipalities are responsible for general upkeep of sidewalks to ensure they remain open and usable to persons with disabilities. However, in practice this may require a more nuanced interpretation of local, state, and federal regulations. Therefore, it is recommended that a land use attorney be consulted prior to enacting any local laws or policy. For a more in-depth overview, please refer to “Land Use Law and Sidewalk Requirements Under the Americans with Disabilities Act” published by the Real Property, Trust and Estate Law Journal, available here: https://ssrn.com/abstract=3019506

2023 Bridge NY applications

Applications for the 2023 Bridge NY solicitation: Hudson Street over Mill Creek in Johnsburg (Warren County) and County Route 3 over Mill Brook in the Town of Putnam (Washington County).