Brian Abare    Village of South Glens Falls DPW 
Stu Baker    Town of Queensbury Community Development 
Dan Barusch    Town of Lake George Planning Department 
Ed Bartholomew    EDC of Warren County 
Rob Cherry    NYSDOT Region 1 
Christina Doughney    CHA 
Ed Doughney    Warren County DPW 
Douglas Frost    Village of Lake George 
Robert Hansen    CME
 
Steve Haskins    Washington County DPW 
Maiken Holmes    Warren County DPW 
Tom Johnson    The Chazen Companies 
Wayne LaMothe    Warren County Planning Department 
Laura Oswald    Washington County Planning 
Dan Rourke    Barton and Loguiduce  
Scott Sopczyk    GGFT 
Jeff Tennyson    Warren County DPW 
Mike Valentine    Saratoga County Planning 
Greg Wichser    NYSDOT Region 1 

Staff
     
Aaron Frankenfeld 
 Kate Mance 

1. Welcome and Introductions ‐ the meeting began at 10:00. 
 
2. Visitors Issues ‐ none 
 
3. Administrative Items 
A. Committee membership update ‐ Aaron listed the new Policy Committee 
membership from Moreau, Kingsbury, Saratoga County, Warren County, and 
Washington County. Committee assignments from the Washington County 
Chairman
 of the Board of Supervisors to A/GFTC have yet to be determined. 
B. Proposed meeting calendar ‐ Aaron reviewed a proposed calendar of TAC and Policy 
Committee meetings. All meetings are scheduled for Wednesdays; start times could 
vary for PC meetings but TAC meetings will begin at 10:00 AM. 
4. Transit 
A. GGFT Update ‐ Scott Sopczyk reported that GGFT ridership for 2015 was the highest 
annual total in the history of the system, up 10.2 % from the previous year. 
Ridership increases are partially attributable to greater utilization by SUNY 
Adirondack students and a healthy tourism season. Capital projects to rebuild some
 
Adirondack / Glens Falls Transportation Council 
11 South Street, Suite 203  
Glens Falls, NY 12801 
p:  (518) 223 – 0086  f:   (518) 223 –  0584 
info@a
gftc.org   www.agftc.org

of the bus engines and to convert the GGFT facility heating system from oil to 
natural gas are complete. 
 
5. UPWP 
A. 2015‐16 Work Program activities (developments since last meeting) 
1) Dix Avenue reassessment ‐ Kate reported that the study committee met on 
12/16 to review data collection results. 2015 
traffic volumes were not as high as 
had been anticipated within the 2000 study. That will result in changes to the 
recommendations that will be carried in the draft report; that report is expected 
by the end of January. 
2) CR 21 / CR 18 Intersection Analysis ‐  Kate reported that the
 study is complete. 
Safety issues appear to be related to poor stop compliance. Recommendations 
are to continue to monitor the  crash data for the location and consider 
implementing incremental improvements, such as additional signing, flashing 
beacons, and rumble stripes, as warranted. 
3) White Creek Watershed Infrastructure Assessment ‐ Aaron  reported that 
Fitzgerald Environmental Associates was under contract and had begun the data 
collection and the hydrology analysis. A meeting has been scheduled with the 
Salem Flood Committee for January 22. Project is on schedule for completion by 
5/1/16.  
4) Exit 18 rezoning ‐ Aaron reported that the technical work from CHA was 
complete.
 A draft report is under review by Town and A/GFTC staff, as well as by 
Warren County DPW and NYSDOT R1 staff. Comments are due to A/GFTC by 
1/22. CHA will meet with owners of large land parcels in the area (early 
February targeted) and finalize the study once comments 
are received. Wayne 
LaMothe requested that the draft materials be sent to him. 
B. 2016 / 2017 Work Program outline ‐ 
1) Review ‐ Aaron reviewed the outline of the draft work program. Incoming new 
funds from FHWA and FTA were unchanged from last year’s amended figures, 
but the amount of the released
 carryover has increased., resulting in a larger 
proposed program. Federal agencies have encouraged efforts to spend down 
carryovers but not necessarily to eliminate them entirely. During the group 
discussion it was determined that the Counties have interest in A/GFTC 
assistance in collecting traffic count data, a portion of the Local 
Transportation 
Engineering and Planning Assistance program could be reserved for a 
solicitation process, and that a proposed Route 9 corridor study should extend 
northward to the intersection of Round Pond Road. 
2) Consideration of Release for Public Comment ‐ A motion was made to release 
the draft UPWP (once it is complete)
 for a public review period. 
 Moved by: Wayne LaMothe  
 Seconded by: Stu Baker    Motion Carried 
 
6. TIP 
A. Amendments and Modifications ‐ Proposed administrative modifications for CR 31 
in Moreau and CR 113 in Greenwich were discussed. Neither will require committee 
action. 
B. Project updates from sponsors ‐ (developments since last
 meeting) 
 Warren County ‐ no new developments   
 Washington County ‐ (Steve Haskins) ‐  Fenimore Bridge painting project is 
complete, construction close‐out ongoing. 
 

 Saratoga County ‐ no new developments. 
 City of Glens Falls ‐ (Ed Bartholomew) reported that consultant selection for 
the Fire Road project was underway. 
 Town of Queensbury ‐ no new developments. 
 NYSDOT ‐ no new project developments. Rob Cherry reported that 
Rosemary Powers, Chief Operating Officer, had left NYSDOT. 
C. TIP
 Development Update ‐ 
1) Local project canvass results ‐ Aaron summarized the projects that have been 
identified by local sponsors as a result of the limited solicitation, totaling 
$37.4M. Approximately $21M over 5 years is available for programming. The 
preservation target is still unclear. Greg Wichser noted that it appears as though
 
sufficient flexibility is available to entertain the requested renewal projects 
provided that the total of those projects does not exceed the total of the 
planning targets. County sponsors noted that project roster were prepared with 
the assumption of a preservation mandate; should that mandate be eliminated, 
the project rosters would 
change. The committee agreed to request the 
exchange of NHPP allocations for STP off‐system bridge funds. Some of the 
projects will have to be programmed in the post‐TIP period due to insufficient 
funds. 
2) Next steps ‐ Aaron said that a subcommittee of local project sponsors and 
NYSDOT will review
 the requested program elements against available planning 
targets and develop a draft TIP that will b e shared with the TAC at the April 20 
meeting, 
 
7. Other Items ‐ Ed Bartholomew announced that the Lt. Governor will be outlining the 
Governor’s budget proposal tomorrow at 10:30 at Crandall Library. Wayne
 LaMothe reported 
that a Department of State grant awarded to Warren County the IBI Group will be for a 
feasibility study of passenger rail improvements between North Creek and Rensselaer station 
will be conducted by the IBI Group. 
 
8. Next meeting / adjourn ‐ The next meeting will be scheduled for
 April 20 at 10:00 AM. A 
motion was made to adjourn the meeting at 11:42. 
Moved by: Wayne LaMothe  
Seconded by: Ed Doughney    Meeting adjourned.